May 4th - 9th

This week’s construction will include the installation of valley gutters and base course along Second Street north of Texas Avenue.  Along with the continuation of construction along phase IV, Constructors, Inc. will also be on the project site to complete the landscaping and electrical needs for the Vaquero unveiling scheduled for May 10th, 10:00am, at the corner of Second & Main.   If you have any questions or concerns please contact Stephanie at MainStreet, 746-1117. 

Construction Phasing Updated

Project Timeline

2nd and Texas - A work in progress! Click to see a larger picture.
May 2
May 17
May 24
May 30
July 10
July 20
July 27
Aug. 6
Aug. 6
Sept. 4
Sept. 4
Sept. 10
Sept. 10
Sept. 17
Sept. 26
Oct. 8
Oct. 18
Oct. 29
Nov. 5
Nov. 13
Nov. 26
Dec 4
Dec. 18
Feb. 1

 

 